[DiaryPoint | Reporter Eom Ju-yong] South Korea’s Ministry of Science and ICT on the 20th proposed draft enforcement decree and rules covering qualification standards and reporting procedures for artificial intelligence data centers (AIDCs), as well as a coordinated permitting process. The proposal would exempt newly built, expanded, or converted AIDCs outside the capital region from power grid impact reviews if their contracted capacity is 50 MW or less.
The draft defines an AIDC as a facility equipped with at least a specified amount of AI accelerators, along with the power and cooling systems needed to operate them. Its design power ratio must be 1.5 or lower. The definition also covers colocation facilities that provide space equipped with power, telecommunications, and cooling infrastructure for AI racks owned or managed by another company.
Operators would have to file a construction notice before work begins and an operating notice at least 30 days before operations start. Changes to a filing must be reported within 30 days of the reason for the change. To prevent operators from filing and then delaying a project to reserve special benefits, the draft requires them to set and report a construction start date within one year of filing.
The 50 MW threshold applies to facilities outside the capital region
The exemption from power grid impact reviews would apply to AIDCs outside the capital region with contracted capacity of 50 MW or less. It would cover new construction, expansions, and conversions of existing facilities into AIDCs. Facilities in the capital region would not qualify under this exemption.
The streamlined reviews for designated special zones are a separate measure from the exemption for facilities of 50 MW or less. The government is pursuing a plan to waive nontechnical reviews for facilities within AIDC special zones. It also plans to establish a fast-track for megaprojects and facilities eligible for coordinated permitting, allowing reviews to begin earlier. The special-zone streamlining and fast-track are being developed by relevant ministries separately from this draft decree.
Under coordinated permitting, an operator would submit the relevant documents at once, and the Ministry of Science and ICT would coordinate procedures with other agencies. The process could continue based on the submitted documents even if an agency fails to respond by the deadline. This does not guarantee that a project will receive the power it needs; review exemptions and access to electricity are separate issues.
The AIDC Special Act is scheduled to take effect on March 10, 2027. Comments on the draft enforcement decree and rules may be submitted through the Public Participation Legislation Center or the Ministry of Science and ICT through December 30. A public hearing will be held at 2 p.m. on December 9 in the international conference room at Nuritkum Square in Mapo-gu, Seoul.
Bae Kyung-hoon, deputy prime minister and minister of science and ICT, said the rules would help operators anticipate which projects qualify for support and the scope of available benefits. The ministry plans to complete the subordinate regulations after the public comment period and legal review, so they can take effect alongside the Special Act.